The Brief

To design, supply, install and commission a residential sprinkler system to a new care home incorporating ground, first and second-floor protection. Fed from its own residential tank and pump.

The challenge

There were delays in completion of works due to Covid-19 pandemic and with main contractor scheduling of programme.

The Solution

FDS installed a fully hydraulically calculated CAT II residential system with 385 sprinkler heads fed from 1no 12m3 tank and residential electric pump complete with integral alarm monitoring to BS9521: 2014.

Project Location: Yatton Extra Care Home, Yatton nr Bristol

Client: Keyplan Engineering Limited

 Project Value: £57,000.00

 Completion: July 2020