FDS has been appointed to carry out fire sprinkler works at the impressive new £48.7million Haverfordwest School.
The new school building, on the former Sir Thomas Picton School site, is due for completion in the summer of 2022.
The new-build will accommodate 1500 pupils aged 11-16 and 250 sixth form pupils.
FDS has been working alongside Whitehead Building Services for the last few months carrying out the 3D design using Revit.
This £500k project for FDS will consist of:
2500 sprinkler heads
8 zone check units
250 meters of 150mm underground mine
Fully pumped water suppliers including a full hold 135m3 sprinkler tank